The safest-looking support layout is often the one that fails. A hot PP-R run clipped solid at every meter looks like careful work. Then the first week of hot water arrives. The pipe tries to grow, and every fusion joint takes an axial load it was never meant to carry. PPR pipe support spacing is two jobs at once: hold the pipe up, and let it move. Do only the first and the line bows, cracks clips, or works its joints loose over the heating season.
The scale surprises crews trained on metal. Standard PP-R expands 0.15 mm per meter per kelvin of temperature rise. Aquatherm puts plain-plastic expansion at 5 to 10 times that of copper or steel. Take the run this page keeps coming back to: ten meters of standard PP-R, installed at 20 °C, operating at 60 °C. The length change is 0.15 × 10 × 40 = 60 mm — a hand’s width of movement in a line the crew already called finished.
One note before the tables. Hitze publishes no approved spacing or expansion values of its own yet, and we say that plainly. The reference numbers below come from the Wefatherm Specification Manual, a German pipe maker’s engineering document, with Techno and aquatherm publications corroborating where noted. Your installed product follows its own supplier’s table. The skill this page teaches is reading any such table correctly.
Key Takeaways
- Spacing depends on OD, wall temperature, construction and orientation. Wefatherm’s table spans 20 mm pipe at 60 cm for 20–50 °C wall temperatures, tightening to 50 cm at 70 °C.
- ΔL = α × L × ΔT. Standard PP-R (α 0.15 mm/m·K) grows 60 mm over 10 m at ΔT 40 K; fiber-composite pipe grows 14 mm on the same run.
- Vertical risers get 20% longer spacing — factor 1.2 — per the note under the manufacturer’s span tables.
- Loop sizing on that d40 run: bending leg Ls = K × √(d × ΔL), K = 15 → 735 mm; expansion bow Amin = 2 × ΔL + 150 mm → 270 mm.
- Exposed runs need compensation. Runs buried in plaster, floor topping or concrete, and shaft risers under 3 m free length, do not.
- Every figure here is an attributed manufacturer value, not a Hitze-approved value. Use your pipe supplier’s own table for the installed product.

Supports and Expansion Are One Design Problem
The two failure signatures point in opposite directions, which is why crews misread them. Space the clips too wide and the pipe sags between them. Hot PP-R is softer than cold, so the droop shows at the low points first and the run reads like a wave. Lock the run solid instead and all 60 mm of the reference run’s movement goes nowhere. Fittings take axial loads they were not fused for, clip liners crack, and long stretches bow sideways at the weakest restraint. Both failures trace back to one missing calculation.
The fix is planning both jobs with one set of numbers. The fixed-point map sets each free length, each free length sets its ΔL, and ΔL sizes both the compensation and the clip spacing that has to live with it. Every section below runs that chain.
The Expansion Formula That Drives Everything
Three inputs, one number
Every support and compensation decision starts from one line of arithmetic: ΔL = α × L × ΔT. ΔL is the length change in millimeters, α the coefficient in mm/m·K, L the free length in meters, ΔT the temperature swing in kelvin. Wefatherm’s own worked example runs 0.15 × 10.0 × 40 = 60 mm.
Coefficients by construction, with their sources
Alpha is where construction changes the answer. Three values matter on this site’s range, and each carries its publisher’s name.
- Standard PP-R: α = 0.15 mm/m·K, printed in the Wefatherm manual and matched by Techno’s TDS.
- Fiber-glass-reinforced pipe: 0.035 mm/m·K (Wefatherm) to 0.05 mm/m·K (Techno), with aquatherm claiming at least a 75% reduction. Quote the range — makers genuinely differ.
- Aluminium-composite PPR (PPR-AL-PPR): about 0.030 mm/m·K, as published on this site’s thermal expansion comparison article.

The formula makes the construction choice concrete. Ten meters at ΔT 40 K grows 60 mm in standard PP-R. Wefatherm’s Table 6.7 prints 14.00 mm for the same run in fiber pipe. Aluminium composite works out near 12 mm, computed from the site-published coefficient.
Which temperature difference counts
ΔT runs from installation temperature to maximum operating temperature — not daily ambient swings, which the pipe flexes through slowly. A line installed at 20 °C and serving a class 1 system at 60 °C runs ΔT 40 K. Class 2 at 70 °C makes it 50 K. The EN ISO 15874 service classes set those bands, and the site’s temperature-rating guide covers what they mean for selection.
Reading a PP-R Support Span Table
Four variables set the spacing
There is no universal PPR pipe clip spacing, and anyone printing one is hiding assumptions. Four things set the spacing a run tolerates. Outside diameter and wall thickness schedule — the SDR and PN ratings define it. Pipe wall temperature in service. Orientation. Construction makes a fifth: fiber pipe is stiffer than standard pipe of the same size, so its table carries longer spans.
The stiffness story explains the temperature rows. PP-R’s flexural modulus is about 800 MPa per ISO 178, already far below metal, and that stiffness falls as the wall warms. Same pipe, same clips, hotter water: the span between brackets gets shorter.
The temperature row is the skill
Look at the d20 row of the Wefatherm standard-pipe table. At a 0 °C wall temperature the required span is 85 cm. At 70 °C it is 50 cm. Same pipe, same clips, same orientation — and the hot line needs clips 41% closer together. One-spacing-per-size blog advice fails exactly here: it quotes the cold row on a hot run, and the sag shows up at commissioning.
Fiber-reinforced pipe runs longer spans at every temperature row of the manufacturer’s tables. The d20 fiber span at 70 °C is 80 cm against 50 cm for standard. Do not let that tempt you into swapping tables between constructions. Each table assumes its own pipe’s stiffness.
Support Spacing by Size and Temperature
The two tables below reproduce the required spans LA from Table 6.8 of the Wefatherm Specification Manual, in centimeters, crossed with pipe wall temperature TR. Values are reproduced as printed — including d75 reading 105 cm at 70 °C, the same as d63, because that is what the manual says.
Required support spans LA (cm) — standard PP-R pipe, sizes d20–d50 (Wefatherm Table 6.8)
| Wall temp TR (°C) | d20 | d25 | d32 | d40 | d50 |
|---|---|---|---|---|---|
| 0 | 85 | 105 | 125 | 140 | 165 |
| 20 | 60 | 75 | 90 | 100 | 120 |
| 30 | 60 | 75 | 90 | 100 | 120 |
| 40 | 60 | 70 | 80 | 90 | 110 |
| 50 | 60 | 70 | 80 | 90 | 110 |
| 60 | 55 | 65 | 75 | 85 | 100 |
| 70 | 50 | 60 | 70 | 80 | 95 |
Required support spans LA (cm) — standard PP-R pipe, sizes d63–d125 (Wefatherm Table 6.8)
| Wall temp TR (°C) | d63 | d75 | d90 | d110 | d125 |
|---|---|---|---|---|---|
| 0 | 190 | 205 | 220 | 250 | 250 |
| 20 | 140 | 150 | 160 | 180 | 190 |
| 30 | 140 | 150 | 160 | 180 | 190 |
| 40 | 130 | 140 | 150 | 170 | 180 |
| 50 | 130 | 140 | 150 | 170 | 180 |
| 60 | 115 | 125 | 140 | 160 | 170 |
| 70 | 105 | 105 | 125 | 140 | 150 |
Vertical risers take the 1.2 factor
Directly under both span tables the manual prints a correction most web pages never republish: for vertical pipelines, increase the relevant distances by 20%, factor 1.2. A riser’s weight loads the clips axially instead of bending the pipe between them. The same d20 line that wants 50 cm spacing horizontally at 70 °C may run 60 cm vertically. Metal-trained crews usually get this backwards and over-clip risers. Only the span distance relaxes; fixed-point placement still follows the section rules.
Whose numbers are these? The spans above are Wefatherm’s, published for Wefatherm pipe. Hitze publishes no approved support-spacing values yet, and no table transfers between makers by analogy. Between temperature rows, take the closer spacing. Before marking a wall, get the span table for the pipe you actually bought.
Fixed Points, Guides and Sliding Supports
Three clamp jobs, three hardware choices
Not every clip does the same job. A fixed point locks the pipe axially — the anchor a section grows from. A guide keeps the line in its route while letting it slide. A sliding support carries weight only and must leave the pipe free to travel along its axis. Hardware follows the job: rigid clamps bolted hard for fixed points, rubber-lined clamps for sliding ones.
One definition keeps the arithmetic honest. The free pipe length is the stretch between two points where the pipe is secured or clamped in a fixed manner. That length — not the total route — is the L in ΔL = α × L × ΔT.
The layout rules that keep the system honest
The manufacturer’s fixed-point rules read like accident reports, because that is where they come from.
- Fixed points divide the network into sections. Measure every free length from a fixed point.
- Sliding clamps positioned each side of a fitting act as fixed points. Keep them clear of fittings that must move.
- Clamps on long standoffs self-align and quietly stop acting as fixed points. Use short, rigid fixings where you intend one.
- Where a branch pipe passes through a wall, mount it fixed.
- Valves and heavy equipment need their own support structure, so no force transfers into the pipe.
- Fix the run at a low ambient temperature. Operating movement then loads the line in compression, which PP-R handles better than joint tension.
The sliding side has its own discipline. Axial movement must not be impeded by loose or sliding supports. Fittings must sit clear of sliding clamps, or the clamp becomes a fixed point you never designed. The site’s PP-R installation guide covers the fusion work itself.

Sizing Bending Legs and Expansion Bows
The bending leg, worked to 735 mm
A bending leg is a free arm of pipe at right angles to the run. When the run grows, the arm flexes and absorbs the movement instead of loading the anchor. The manual sizes it with Ls = K × √(d × ΔL): d in millimeters of OD, ΔL in millimeters of expansion. K is a material constant — 15 for Wefatherm pipes. The attribution matters, because other makers publish other constants.
Back to the reference run, now specified as d40 with 60 mm of growth. Ls = 15 × √(40 × 60) = 15 × √2400 ≈ 735 mm. That is the minimum free arm that absorbs the section’s movement without overstressing the fittings at its root. If the run already turns within the section, the turning arm can serve as the leg. Check its length against the same Ls before adding a dedicated loop.
Expansion bows and the pre-stressed option
Where the route gives no direction change, build an expansion bow — a U-shaped offset in the run. Its minimum width follows Amin = 2 × ΔL + SA, with SA a 150 mm safety distance to any structure. For the 60 mm reference run: 2 × 60 + 150 = 270 mm wide. Leave that clearance in both directions of travel.
The third option is pre-stressing. Pull the leg halfway through its travel at installation, and the hot run sits centered. The formula halves the expansion input: LsV = K × √(d × ΔL/2). For the same run that gives 15 × √(40 × 30) ≈ 520 mm — a shorter leg for the same duty. The trade-off is installation care: the cold pull must be set and held while the fixing is made.
When You Can Skip Expansion Compensation
Not every run needs a loop. The decision is a laying-situation matrix, not a pipe-size rule. The manual’s Table 6.5 reads cleanly.
- Exposed laying: yes — take expansion compensation measures.
- Laying in shafts and rising mains: no compensation where the free length is under 3 m.
- Buried laying in plaster, floor topping or concrete: no — the surrounding build-up absorbs the movement.
The matrix removes the loop, not the physics. An encased run still expands when it heats. With no free arm available, the fittings and penetrations absorb the movement instead. Branch tees on long encased runs therefore deserve the same attention as exposed ones. The force has not disappeared. It has been redirected into your joints.
On insulated runs, one more weight enters the calculation. The manual is explicit: when establishing bracket distances, the weight of the insulation should be taken into account.
At commissioning, skipped compensation reads in three places: bowed runs between restraints, fusion joints weeping or stress-whitened at direction changes, and cracked or displaced clip liners. None of these announce themselves on day one. They accumulate over heating cycles — exactly when nobody is watching anymore.
Standard vs Fiber vs Aluminium Composite Runs
Same ten-meter run, same 40 K swing, three constructions. The table pairs each published coefficient with the expansion it produces and the effect on the support plan. Fiber spans 14–20 mm because makers publish 0.035 to 0.05 mm/m·K; the composite figure is computed from the site-published coefficient.
The same 10 m hot run in three constructions (ΔT 40 K)
| Construction | α (mm/m·K) | ΔL (mm) | Support spans | Compensation load |
|---|---|---|---|---|
| Standard PP-R | 0.15 | 60 | Baseline spans (tables above) | Full: legs or bows on every exposed section |
| Fiber-reinforced PPR-FB-PPR | 0.035–0.05 | 14–20 | Longer at every temperature row | Legs and bows shrink with ΔL |
| Aluminium composite PPR-AL-PPR | ~0.030 | ~12 | Follow supplier’s composite table | Smallest movement of the three |

What disappears with reinforced construction is movement — three to five times less growth, and loop dimensions shrink with it. The fiber span tables buy a second saving: fewer clips. On the Wefatherm tables a d20 fiber line runs 80 cm at 70 °C against 50 cm for standard. A d32 runs 110 against 70, a d63 runs 155 against 105. On a long riser that is real labor and hardware back.
What does not disappear is the need for supports. Reinforced pipe still sags if spaced like metal, and it still needs fixed points defining its sections. The honest trade: reinforced constructions cost more per meter and buy back clips, loops and installation time. Let exposure and ΔT decide, not habit. On exposed class 1 and class 2 risers over a few meters, fiber is the stronger buy. On short embedded branches, standard PP-R does the job.
The Hitze range carries all three constructions in OD 20 to 110 mm, socket-fusion jointed: standard and ceramic-core PP-R, fiber-glass-reinforced PPR-FB-PPR for reduced thermal expansion, and PPR-AL-PPR aluminium composite. The PP-R pipe and fittings range page lists them side by side.
Fiber vs standard changes both the expansion and the clip count on a hot run. Compare the constructions in person and get samples with the spec sheet. Standard, PPR-FB-PPR and PPR-AL-PPR run across OD 20–110 mm.
Standard PP-R | PPR-FB-PPR | PPR-AL-PPR · OD 20–110 mm · Socket heat fusion
Laying Out Supports on a Hot Run
Everything above collapses into one marking sequence. Run it per section, not per floor, because the fixed-point map is what the sequence is really drawing.
- Fix the temperatures: design operating temperature and coldest credible installation temperature. The difference is your ΔT.
- Place the fixed points first, dividing the run into sections. Each section’s free length L feeds everything after.
- Compute ΔL = α × L × ΔT per section, with the coefficient of the construction you actually bought.
- Read the supplier’s span table at your size and wall-temperature row. Mark clip positions. Between rows, take the closer spacing.
- On verticals, apply the 1.2 factor to those distances.
- Size compensation at each section end. A bending leg of at least K × √(d × ΔL), a bow of at least 2 × ΔL + 150 mm, or a direction-change arm checked against the same leg length.
- Keep 150 mm of safety distance between moving pipe and structure, in both directions of travel.
- Fit rubber-lined clamps, snug not crushed. Keep sliding points clear of fittings. Put valves on their own supports.
- Fix the run cold, at the lowest ambient before commissioning.
Then record the result. A handover sketch shows every fixed point, sliding zone and loop dimension. It separates a maintenance crew that understands the run from one that adds a clip exactly where movement needed to be free. It costs ten minutes and protects every warranty conversation after it.
Conclusion
Support spacing and thermal expansion are one calculation on a hot PP-R line, and doing them separately is how runs sag or load their own joints. The arithmetic is short: ΔL from the coefficient, spans from the supplier’s temperature row, compensation from the same ΔL. The discipline is attribution — knowing whose numbers you marked on the wall.
- Read the span table at your wall-temperature row. A d20 line tightens from 60 cm at 20 °C to 50 cm at 70 °C in the Wefatherm table — a 17% drop most layouts miss.
- Vertical risers take the 1.2 factor: spacing relaxes 20% where the pipe’s weight loads clips axially.
- The compensation chain on the reference run: 60 mm growth → 735 mm bending leg → 270 mm bow → 520 mm pre-stressed leg.
- No Hitze-approved spacing values exist yet. The figures here are manufacturer-published and attributed. The installed product follows its own supplier’s table.
The risk hides where you cannot see after the wall closes. An over-clipped run loads its fusion joints every heating cycle, and the weep surfaces years later at a direction change. Before marking the next riser, get the span table that belongs to your pipe — or request samples and the spec sheet if the construction choice is still open.
Frequently Asked Questions
How far apart should PPR pipe supports be on a hot-water line?
No single spacing exists — OD, wall temperature, construction and orientation all matter. Wefatherm’s table spans 20 mm pipe at 60 cm for 20–50 °C wall temperatures and 50 cm at 70 °C, with 20% more allowed on verticals. Use your own supplier’s table for the installed product.
Does PPR pipe need expansion loops?
Only where a free length can move. Exposed laying requires compensation; runs buried in plaster, floor topping or concrete, and shaft risers under 3 m free length, do not. Size from ΔL = α × L × ΔT on the free length, not from pipe size.
What is the thermal expansion coefficient of PPR pipe?
Standard PP-R runs 0.15 mm per meter per kelvin, published by both Wefatherm and Techno. Fiber-glass composite pipe publishes 0.035–0.05 depending on maker, and aluminium-composite PPR about 0.030 — roughly 70–75% less movement to design out.
Do vertical PPR risers need different support spacing?
Yes. The manufacturer span tables allow 20% longer spacing on vertical runs, factor 1.2, because the pipe’s weight loads the clips axially rather than in bending. Fixed-point placement still follows the section rules.
Can I use the same support spacing as copper or steel pipe?
No. PP-R’s flexural modulus is about 800 MPa — far less stiff than metal — and its stiffness falls further as the wall warms. Hot plastic runs need closer clips, and metal spacing tables assume zero axial growth, which PP-R guarantees.




